1. Site Plan Package |
2. Design Review Package |
3. Binding Site Plan Package |
4. Administrative Deviations Request |
5. Letters of Completeness |
6. SEPA Documents |
| a. LUA2019-0082 - Planned Action Certification Application for Costco |
| b. LUA2019-0068 - Planned Action Certification for the public roads of 91st Ave SE and S. Lake Stevens Road Connector |
| c. LUA2019-0069 - An MDNS for the construction of 24th St SE |
| d. Planned Action Ordinance 878, September 24, 2012 |
| e. 2012 Draft and Final 20th Street SE Corridor Subarea Plan Environmental Impact Statements |
7. Public Notification |
| a. Notice of Applications for the site plan, design review, and planned action certification |
| b. Notice of Public Meeting for site plan and design review |
| c. Notice of Application for the binding site plan |
8. Public Meeting Sign-in Sheet |
9. Design Review Recommendation |
10. Public Comments |
| a. Agency Letters and Emails (received from April 22, 2019 to March 27, 2020) |
| b. All comments received (verbatim) by form (letters, emails, etc.) (received from April 22, 2019 to November 19, 2019) |
|
| i. SEPA Public Comments |
|
| ii. Developer Agreement Comments |
|
| iii. Site Plan and Design Review |
|
| iv. BSP Comments |
| c. Public Comments received after November 19, 2019 |
11. Response Letters to Public Comments |
|
| a. City of Lake Stevens Summary Response to Public Comments for Costco dated November 19, 2019 |
|
| b. Letter from City of Lake Stevens to Snohomish County dated November 19, 2019 |
|
| c. Letter from Stoel Rives LLP to City of Lake Stevens dated November 8, 2019 |
12. Environmental Reports |
A. Critical Areas |
| 1. Critical Areas Report, by Sewall Wetland Consulting, Inc. dated February 18, 2019, revised September 10, 2019 |
| 2. Habitat Report, by Sewall Wetland Consulting, Inc. dated February 18, 2019 |
| 3. Impacts and Mitigation Report, by Sewall Wetland Consulting, Inc. dated September 17, 2019, revised November 15, 2019 |
| 4. Revised Avoidance, Impacts and Mitigation Report by Sewall Wetland Consulting, Inc., dated November 15, 2019, received on November 21, 2019, revised February 10, 2020, revised April 6, 2020 |
| 5. Critical Area Mitigation Plan, by Sewall Wetland Consulting, Inc. dated September 10, 2019, revised November 8, 2019, revised January 20, 2020, revised April 6, 2020 |
| 6. Mitigation Bank Use Plan Costco Lake Stevens and City of Lake Stevens 24th Street Extension Project NWS by Sewall Wetland Consulting, Inc. dated January 25, 2019, revised September 10, 2019, revised November 15, 2019, revised February 10, 2020, revised April 6, 2020 |
| 7. Critical Area Exhibits by Sewall Wetland Consulting, Inc. dated June 6, 2018 |
| 8. Costco Lake Stevens & SE 24th Street Extension – Alternatives analysis, by Sewall Wetland Consulting, Inc. dated February 19, 2019 |
| 9. Alternatives Analysis for Costco Wholesale, Lake Stevens by Sewall Wetland Consulting, Inc. dated October 21, 2019, revised February 10, 2020 |
| 10. Biological Evaluation, Cedarock Consultants, Inc., dated August 13, 2019, revised February 10, 2020 |
| 11. Recommended Culvert Sizing Analysis - Lake Stevens Road at SR-9, by Cedarock Consultants, Inc., dated March 26, 2019 |
| 12. Recommended Culvert Sizing Analysis – Mosher Creek and Tributary, by Cedarock Consultants, Inc., dated August 14, 2019 |
| 13. Wetland and Stream Delineation Report 24th Street Southeast Extension by The Watershed Company, dated September 7, 2017, revised May 30, 2018 |
| 14. Wetland and Stream Delineation for 39.74-Acre Aggregate Property Lake Stevens, WA, by Altmann Oliver Associates, LLC dated September 21, 2012 |
| 15. Lake Stevens Costco Peer Review of Critical Area & Culvert Design Documentation Technical Memorandum by The Watershed Company, dated November 20, 2019 |
| 16. Lake Stevens Costco 2nd Peer Review of Wetland Mitigation by The Watershed Company, dated March 13, 2020 |
B. Traffic |
| 1. Draft Traffic Impact Analysis (TIA), by Transportation Solutions, Inc dated August 31, 2018 |
| 2. Final Traffic Impact Analysis (TIA), by Transportation Solutions, Inc dated October 26, 2018 |
| 3. 24th Street/South Lake Stevens Road Intersection Control Evaluation Draft Report, by Transportation Solutions, Inc. |
| 4. SR-9, MP 13.80, 24th St SE/ South Lake Stevens Road Intersection Control Evaluation, by Transportation Solutions, Inc. dated October 2018 |
| 5. Traffic Impact Analysis Simulation Analysis Findings Technical Memorandum, by Transportation Solutions, Inc dated March 12, 2019, revised August 12, 2019 |
| 6. No Connection from 24th Street SE to S Lake Stevens Road Technical Memorandum, by Transportation Solutions, Inc dated September 9, 2019 |
| 7. Costco Parking Needs Assessment, by Kittelson & Associates dated May 6, 2019 |
C. Stormwater and Drainage |
| 1. Preliminary Drainage Report, by DOWL Engineering Inc., dated September 18, 2019 |
| 2. Draft Stormwater Site Plan, by DOWL Engineering Inc., dated February 2020 |
| 3. 24th Street Improvement Project Preliminary Stormwater Site Plan, by Lochner dated January 2018 |
D. Geotechnical |
| 1. Geotechnical Engineering Report, by Terracon Consultants, Inc. dated May 29, 2018 |
| 2. Preliminary Geotechnical Report 24th Street SE Extension Lake Stevens, by HWA GeoSciences Inc., January 15, 2016 |
| 3. Draft Geotechnical Report 24th Street SE Final Design, HWA GeoSciences Inc. dated October 16, 2017 |
| 4. Draft Supplementary Geotechnical Report 24th Street SE Final Design, by HWA GeoSciences Inc. dated April 12, 2018 |
| 5. Draft Geotechnical Report 24th Street SE and 91st Avenue SE Extensions, by HWA GeoSciences Inc. dated April 9, 2019 |
E. Cultural Resources |
| 1. Archaeological Survey and Assessment, State Route 9 and 20th Street Southeast, by Caldera Archaeology dated May 5, 2018 |
F. Trees |
| 1. Arborist Report 24th St SE Extensions – Lake Stevens, by H.W. Lochner, Inc dated November 1st, 2017 |
G. Other |
| 1. City of Lake Stevens 24th Street Extension Project Phase I Environmental Site Assessment by Lochner, dated January 2018 |